[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384907,165,1,"单选题","以下各项中，（）属于整体变更控制的输入。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已批准的纠正措施",false,{"key":16,"text":17,"correct":14},"B","已批准的预防措施",{"key":19,"text":20,"correct":14},"C","已批准的缺陷修复",{"key":22,"text":23,"correct":24},"D","绩效报告",true,"整体变更控制的主要输入有：项目计划、绩效报告、变更请求、可交付物 已批准的纠正措施、已批准的预防措施、已批准的缺陷修复等属于整体变更控制的输出。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]