[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384904":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384904,165,1,"单选题","某软件开发项目进度紧迫，在设计方案还没完成前，项目经理改变计划，停止设计工作，要求项目组成员立即转入代码编写。关于项目经理的行为，下面说法正确的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理的行为不妥，等CCB批准后方可改变计划",true,{"key":16,"text":17,"correct":18},"B","项目经理有权改变流程，不需审批",false,{"key":20,"text":21,"correct":18},"C","这种行为属于赶工，项目经理可直接安排实施",{"key":23,"text":24,"correct":18},"D","这种行为属于快速跟进，项目经理有权决定","项目经理的行为不妥，变更要经过一定的流程，需要变更委员会批准，即等CCB批准后方可改变计划",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]