[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384902,165,1,"单选题","以下关于变更的流程和规则的做法中，（）是错误的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以口头方式提出某项变更，在评估前针对该变更提交了书面报告",false,{"key":16,"text":17,"correct":14},"B","项目组成员变更以邮件发出，在评审前填写了变更申请",{"key":19,"text":20,"correct":21},"C","为了规范，监理不对变更进行分级，所有变更流程都不能简化",true,{"key":23,"text":24,"correct":14},"D","按照影响范围、紧急程度把变更分为3个优先级别","变更提出的方式可以多样，只要在评估前以书面形式提出即可；按照影响范围、紧急程度把变更分为重大、重要、一般三个优先级别；为了突出效率，对于小项目通常可以进行简化变更流程。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]