[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384897,165,1,"单选题","在项目变更时，如果有人要求项目进度提前，那么根据变更控制流程，首先应该()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提交书面的进度变更申请单",true,{"key":16,"text":17,"correct":18},"B","变更的影响分析",false,{"key":20,"text":21,"correct":18},"C","对该变更接受或拒绝",{"key":23,"text":24,"correct":18},"D","执行变更","项目变更的第一步，就是提交正式的变更申请。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]