[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384892":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384892,165,1,"单选题","变更常常是项目干系人由于项目环境或者是其他各种原因要求对项目的范围基准等进行修改。如某项目由于行业标准变化导致变更，这属于（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目实施组织本身发生变化",false,{"key":16,"text":17,"correct":14},"B","客户对项目、项目产品或服务的要求发生变化",{"key":19,"text":20,"correct":21},"C","项目外部环境发生变化",true,{"key":23,"text":24,"correct":14},"D","项目范围的计划编制不周密详细","变更产生的原因：?项目外部环境发生变化；?项目范围的计划编制不周密详细，有一定的错误或遗漏；?市场上出现了或是设计人员提出了新技术、新手段或新方案；?项目实施组织本身发生变化；?客户对项目、项目产品或服务的要求发生变化。本题中的情况显然属于项目的外部环境发生了变化。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]