[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384890,165,1,"单选题","某项目开始一段时间后，客户提出一些产品修改需求，项目组小A没有通知项目经理变执行了变更。测试阶段发现，测试结果与设计不同。这种情况主要是由于 （） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","测试计划制定不完善",false,{"key":16,"text":17,"correct":18},"B","范围变更控制没有做好",true,{"key":20,"text":21,"correct":14},"C","质量管理计划制定不完善",{"key":23,"text":24,"correct":14},"D","沟通计划不完善","本题因为变更控制没有做好，才导致了测试结果与设计不同。其他选项不是主要原因。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]