[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384888":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384888,165,1,"单选题","某系统集成公司据经验决定建立一套变更控制系统，为保证该系统行之有效，该系统中必须包括的内容是()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对每个项目的各条功能和物理特征作出的具体描述",false,{"key":16,"text":17,"correct":14},"B","项目预期的、具体的变更要求，以及响应计划",{"key":19,"text":20,"correct":21},"C","定义项目文件如何变更的程序和规则",true,{"key":23,"text":24,"correct":14},"D","预测项目变更的绩效报告","变更控制系统应包括关于“变更申请、变更评估、得到变更控制委员会的批准或拒绝、变更程序、影响分析、过程记录等”的规定。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]