[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384885,165,1,"单选题","变更管理的工作程序包括：接受变更申请、对变更的初审、（）、CCB决定是否批准、发出变更通知并开始实施、变更实施监控、变更效果评估。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变更实施",false,{"key":16,"text":17,"correct":18},"B","变更方案论证",true,{"key":20,"text":21,"correct":14},"C","组建CCB",{"key":23,"text":24,"correct":14},"D","判断发生变更的项目是否己纳入正常轨道","本题考查变更的流程，主要包括：申请、初审、论证、批准、实施、监控、评估。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]