[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384884,165,1,"单选题","以下关于变更控制委员会CCB的描述中，（）是正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","CCB是作业机构",false,{"key":16,"text":17,"correct":14},"B","CCB在审批变更时要提出变更",{"key":19,"text":20,"correct":14},"C","CCB项目经理不能进入",{"key":22,"text":23,"correct":24},"D","CCB的权利包含对储备资源的授权",true,"CCB是决策机构，只负责决策，不提出方案，CCB可以是一个人，项目经理可以是CCB的成员。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]