[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384882,165,1,"单选题","（ ）不属于变更控制过程所包含的变更管理活动",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","识别可能发生的变更",false,{"key":16,"text":17,"correct":14},"B","维持所有基线的完整性",{"key":19,"text":20,"correct":14},"C","完成防灾演习等特定工作",{"key":22,"text":23,"correct":24},"D","系统升级",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]