[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384880,165,1,"单选题","某企业的管理系统已进入试运行阶段，公司领导在试用该系统时认为他使用的出差报销表格的栏目设置不合理，便电话要求负责系统建设的项目经理修改，根据变更管理的要求，项目经理正确的做法是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","告诉公司领导，项目试运行结束后再统一修改",false,{"key":16,"text":17,"correct":14},"B","让开发人员修改，再通知公司领导确认",{"key":19,"text":20,"correct":21},"C","将公司领导的要求记录下来，确认变更内容后提出正式的变更申请",true,{"key":23,"text":24,"correct":14},"D","亲自督促对该表格的修改，完成后亲自确认并向公司领导汇报。","教程 P420，变更管理工作程序，这个一定需要掌握。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]