[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384876,165,1,"单选题","某大型系统集成项目由多个不同的承包商协作完成，项目涉及了分别代表7家公司的24个主要干系人、项目经理陈某直接管理的团队由7个项目小组长，每个项目小组长负责一支约15人的工作组。陈某意识到必须特别注意进行有效的整体变更控制，这表明他最应该关心的工作是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","整合从项目的不同专业职能部门交付来的工作成果",false,{"key":16,"text":17,"correct":14},"B","设立一个专门的变更控制部门来监控所有的项目变更",{"key":19,"text":20,"correct":14},"C","保持基准计划的完整性。整合产品和项目的范围，并且协调那些跨知识领域的变更",{"key":22,"text":23,"correct":24},"D","关注可能引发变更的因素，确定已经发生的变更并管理实际发生的变更",true,"题目已经说了陈某意识到必须特别注意进行有效的整体变更控制，所以用排除法可知，参考答案是D。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]