[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384874,165,1,"单选题","以下关于需求变更策略的叙述中，（）是错误的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","所有需求变更必须遵循变更控制过程",false,{"key":16,"text":17,"correct":14},"B","对于未获得核准的变更，不应该做变更实现工作",{"key":19,"text":20,"correct":21},"C","完成了对某个需求的变更之后，就可以删除或者修改变更请求的原文档",true,{"key":23,"text":24,"correct":14},"D","每一个需求变更必须能追溯到一个经核准的变更请求","变更完成之后，变更的原始文档资料必须保存。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]