[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384851,165,1,"单选题","某企业在项目实施过程中，为降低项目成本、更好的满足客户需求，按照以下流程对项目所需的部分产品进行了采购：① 记录项目对于产品、服务或成果的需求，并且寻找潜在的供应商；② 从供应商处获取相关信息、报价和建议书；③ 审核所有建议书，在供应商中进行选择，并与选中者谈判签订最终合同；④ 管理合同以及买卖双方的关系，并管理与合同相关的变更。该企业的采购流程缺少了()环节。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制采购计划",true,{"key":16,"text":17,"correct":18},"B","编制询价计划",false,{"key":20,"text":21,"correct":18},"C","询价、招投标",{"key":23,"text":24,"correct":18},"D","合同管理和收尾","很明显，该企业的采购流程缺少了“A．编制采购计划”环节",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]