[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384830,165,1,"单选题","项目工作说明书是对项目提供的产品、成果或服务的描述，其内容一般不包括（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","服务人员",false,{"key":16,"text":17,"correct":18},"B","技术方案选择",true,{"key":20,"text":21,"correct":14},"C","验收标准",{"key":23,"text":24,"correct":14},"D","收费及付款方式","本题考查的是工作说明书的包含内容，要掌握。 教程P390，工作说明书包括的主要内容有前言、服务范围、方法、假定、服务期限和工作量估计、双方角色和责任、交付资料、完成标准、顾问组人员、收费和付款方式、变更管理等。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]