[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384829,165,1,"单选题","下述关于项目合同索赔处理的叙述中，不正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按业务性质分类，索赔可分为工程索赔和商务索赔",false,{"key":16,"text":17,"correct":18},"B","项目实施中的会议纪要和来往文件等不能作为索赔依据",true,{"key":20,"text":21,"correct":14},"C","建设单位向承建单位要求的赔偿称为反索赔",{"key":23,"text":24,"correct":14},"D","项目发生索赔事件后一般先由监理工程师调解","索赔必须以合同为依据。根据我国有关规定，索赔应依据下面内容。?国家有关的法律如《合同法》、法规和地方法规。?国家、部门和地方有关信息系统工程的标准、规范和文件。?本项目的实施合同文件，包括招标文件、合同文本及附件。?有关的凭证，包括来往文件、签证及更改通知，会议纪要，进度表，产品采购等。?其他相关文件，包括市场行情记录、各种会计核算资料等。故B项目实施中的会议纪要和来往文件等可以作为索赔依据，可见B是错误的",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]