[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384827,165,1,"单选题","某办公大楼的开发商将办公楼的智能楼宇系统承包给H公司，双方签订了合同，开发商还聘请了监理方对此项目进行监理。期间，消防子系统验收延误，开发商认为是H公司的责任，向监理方提出了索赔要求。关于索赔流程，下列说法中， （ ） 是正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开发商应在验收延误事件发生后20天内提出索赔意向通知",false,{"key":16,"text":17,"correct":14},"B","监理方收到索赔通知后，应在28天内帮助开发商编制出索赔报告",{"key":19,"text":20,"correct":14},"C","监理方应在索赔报告中充分论证该事件的确为开发商带来了损失，并提出具体的赔偿方案",{"key":22,"text":23,"correct":24},"D","如果H公司不同意监理方做出的索赔决定，可提请仲裁或法律诉讼",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]