[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384815,165,1,"单选题","某机构信息系统集成项目进行到项目中期，建设单位单方面终止合作，承建单位于2010年7月1日发出索赔通知书，承建单位最迟应在 （ ） 之前向监理方提出延长工期和（或）补偿经济损失的索赔报告及有关资料。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2010年7月31日",false,{"key":16,"text":17,"correct":14},"B","2010年8月1日",{"key":19,"text":20,"correct":21},"C","2010年7月29日",true,{"key":23,"text":24,"correct":14},"D","2010年7月16日","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]