[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384796,165,1,"单选题","以下关于合同变更的叙述中，（）是不正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同变更一般处理程序如下：变更的提出、变更请求的审查、变更的批准、变更的实施",false,{"key":16,"text":17,"correct":18},"B","变更申请可以以口头形式提出，变更评估必须采取书面方式",true,{"key":20,"text":21,"correct":14},"C","对于任何变更的评估都应该有变更影响分析",{"key":23,"text":24,"correct":14},"D","合同变更的处理由合同变更控制系统来完成","《系统集成项目管理工程师教程》P339：变更申请、变更评估和变更执行等必须以书面形式出现。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]