[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384794,165,1,"单选题","某软件开发项目合同规定，需求分析要经过客户确认后方可进行软件设计。但建设单位以客户代表出国、其他人员不知情为由拒绝签字，造成进度延期。软件开发单位进行索赔一般按()顺序较妥当。①由该项目的监理方进行调解②由经济合同仲裁委员会仲裁③由有关政府主管机构仲裁",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":18},"B","①③②",true,{"key":20,"text":21,"correct":14},"C","③①②",{"key":23,"text":24,"correct":14},"D","②①③","索赔是在工程承包合同履行过程中，当事人一方由于另一方未履行合同所规定的义务而遭受损失时，向另一方提出索赔要求的行为。项目发生索赔事件后，—般先由监理工程师调解，若调解不成，由政府建设主管机构进行调解，若仍调解不成，由经济合同仲裁委员会进行调解或仲裁。在整个索赔过程中，遵循的原则是索赔的有理性、索赔依据的有效性、索赔计算的正确性。根据上述索赔程序，应选择 B",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]