[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384783,165,1,"单选题","如果承建单位项目经理由于工作失误导致采购的设备不能按期到货，施工合同没有按期完成，则建设单位可以要求 （ ） 承担责任。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承建单位",true,{"key":16,"text":17,"correct":18},"B","监理单位",false,{"key":20,"text":21,"correct":18},"C","设备供应商",{"key":23,"text":24,"correct":18},"D","项目经理","承建单位项目经理由于工作失误导致的责任当然需要承建单位承担责任，本题的干扰项在答案D，但由于建设单位和承建方的项目经理没有合同关系，不能直接要求项目经理承担责任。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]