[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384771,165,1,"单选题","按照索赔程序，索赔方要在索赔通知书发出后 （ ） 内，向监理方提出延长工期和（或）补偿经济损失的索赔报告及有关资料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2周",false,{"key":16,"text":17,"correct":18},"B","28天",true,{"key":20,"text":21,"correct":14},"C","30天",{"key":23,"text":24,"correct":14},"D","3周","按照索赔程序，当出现索赔事项时，首先由索赔方以书面的索赔通知书形式，在索赔事项发生后的28天以内，向监理工程师正式提出索赔意向通知书。 在索赔通知书发出后的28天内，向监理工程师提出延长工期和（或）补偿经济损失的索赔报告及有关资料。因此选择B。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]