[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384748,165,1,"单选题","某项目的现状是：已经被按照沟通计划发布了项目信息；一些项目可交付物成果发生了变更；这些变更是按照变更控制计划做出的；一位干系人在得知以前曾经公布过的项目可交付物成果变更时，感觉十分惊讶；其余干系人都收到了变更通知的消息。针对这种情况，项目经理应该()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","告知干系人信息公布的日期",false,{"key":16,"text":17,"correct":14},"B","审核沟通计划，确定为什么干系人不理解自己的职责",{"key":19,"text":20,"correct":21},"C","对沟通计划进行审核，如需要，对沟通计划进行修改",true,{"key":23,"text":24,"correct":14},"D","在下次项目工作会议上说明该问题，以便其他干系人不会遗忘公布的变更信息","应该确保信息接收人完整地收到信息并理解信息。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]