[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384739,165,1,"单选题","状态会议的目的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","交换项目信息",true,{"key":16,"text":17,"correct":18},"B","让团队成员汇报正在执行的工作",false,{"key":20,"text":21,"correct":18},"C","签发工作授权",{"key":23,"text":24,"correct":18},"D","确认团队提交的成本的准确性","沟通管理项目中的会议 有延伸 项目状态／评审会议的主要目的是： 介绍项目进展情况；项目是否偏离进度计划，若偏离，应采取什么样的措施；说明造成进度偏离计划的原因和如何在今后的工作中防止偏差；汇报在项目执行中发现的问题及潜在的问题，如何解决所发现的问题及如何防止潜在的问题发生；应引起客户或项目负责人注意的事项，如客户可能尚未签署某一文件等。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]