[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384698,165,1,"单选题","项目人力资源计划编制完成以后，不能得到的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","角色和职责的分配",false,{"key":16,"text":17,"correct":14},"B","项目的组织结构图",{"key":19,"text":20,"correct":14},"C","人员配置管理计划",{"key":22,"text":23,"correct":24},"D","项目团队成员的人际关系",true,"人力资源计划应该包括但不限于以下内容：角色和职位的分配、项目的组织结构图、人员配备管理计划。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]