[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384691,165,1,"单选题","责任分配矩阵式一种常用的描述项目角色和职责的方式，关于责任分配的说法错误的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在反映团队成员个人与其承担的工作时，责任分别配矩阵不够直观",true,{"key":16,"text":17,"correct":18},"B","责任分配矩阵可以分成多个层级",false,{"key":20,"text":21,"correct":18},"C","高层级的责任分配矩阵可以界定团队中的哪个小组负责工作分解中的哪一部分工作",{"key":23,"text":24,"correct":18},"D","底层级的责任分配矩阵用来在小组内为具体活动分配角色、职责层次","反映团队成员个人与其承担的工作之间联系的方法有多种，而责任分配矩阵(RAM)是最直观的方法。责任分配矩阵，就是一个表格，上面有活动（一般纵向）、人员（一般横向），在人员和活动之间确定责任分配关系。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]