[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384682,165,1,"单选题","项目经理在项目管理时使用了下图，该图是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","责任分配矩阵",true,{"key":16,"text":17,"correct":18},"B","沟通计划表",false,{"key":20,"text":21,"correct":18},"C","列表式WBS",{"key":23,"text":24,"correct":18},"D","组织结构分解图","任务分配矩阵或称责任分配矩阵（Responsibility Allocation Matrix，RAM）：用来表示需要完成的工作由哪个团队成员负责的矩阵，或需要完成的工作与哪个团队成员有关的矩阵。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]