[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384664,165,1,"单选题","过程改进计划详细说明了对项目管理过程和产品开发过程进行分析的各个步骤，有助于识别增值活动。在项目管理知识领域，过程改进计划产生于（ ）阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量规划",true,{"key":16,"text":17,"correct":18},"B","实施质量保证",false,{"key":20,"text":21,"correct":18},"C","控制质量",{"key":23,"text":24,"correct":18},"D","质量改进","过程改进计划是质量规划阶段的输出。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]