[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384653,165,1,"单选题","控制图中的控制上限和控制下限标明()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","客户将要接受的界限",false,{"key":16,"text":17,"correct":14},"B","可能出现的过程的偏差范围",{"key":19,"text":20,"correct":21},"C","可以接受的过程的偏差范围",true,{"key":23,"text":24,"correct":14},"D","判断项目成败的统计控制点","控制图中的控制上限和控制下限标明可以接受的过程的偏差范围。控制限值比规范限值的限制力度更强。这样，如果一个数据在控制限值范围之外，但是，也可以仍旧在规范限值范围之内。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]