[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384637,165,1,"单选题","项目的质量保证不包括人员的质量保证采用的方法和技术不包括（）.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定质量目标",true,{"key":16,"text":17,"correct":18},"B","确定保证范围的等级",false,{"key":20,"text":21,"correct":18},"C","质量检验",{"key":23,"text":24,"correct":18},"D","制定质量保证规划","项目的质量保证包括产品、系统、服务的质量保证。项目质量保证采用的一些方法、技术主要包括：制定质量保证规划、质量检验、确定保证范围和等级、质量活动分解。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]