[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384614,165,1,"单选题","某项目计划成本为400万元，计划工期为4年，项目进行到两年时，监理发现预算成本为200万元，实际成本为100万元，挣值为50万元，则项目成本偏差为 （ ） 万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","150",false,{"key":16,"text":17,"correct":18},"B","-50",true,{"key":20,"text":21,"correct":14},"C","-150",{"key":23,"text":24,"correct":14},"D","50","本题中PV=200，AC=100，EV=50。CV=EV-AC=50-100=-50",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]