[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384613,165,1,"单选题","某ERP软件开发项目共有12个模块，项目经理对较件进行了成本预算，预算每个模块的开发成本为5万元，按照项目管理计划，每月开发一个模块，12个月完成开发工作。在项目进行到第3个月底的时候，项目经理对照计划，发现刚完成了2个模块的开发工作，经统计，实际花费的成本为15万元。若按照目前的绩效情况，到所有模块开发完成时预计托费的总成本为()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","90万",true,{"key":16,"text":17,"correct":18},"B","75万",false,{"key":20,"text":21,"correct":18},"C","70万",{"key":23,"text":24,"correct":18},"D","66.7万","纯逻辑计算 15*12\u002F2=90万元",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]