[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384610,165,1,"单选题","某软件系统项目成本控制采用了挣值分析技术，假设当前状况数据是PV=4400元，EV=4000元，AC=5000元，BAC=10000元。则该项目的CPI、EA C、当前的项目的状态分别是 （） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.8，12500元，进度滞后、成本超支",true,{"key":16,"text":17,"correct":18},"B","0.8，10000元，进度提前且成本超支",false,{"key":20,"text":21,"correct":18},"C","1.25，12500元，进度滞后且成本低于预算",{"key":23,"text":24,"correct":18},"D","1.25，10000元，进度提前且成本低于预算","CPI = EV\u002F AC=4000\u002F5000=0.8，表明成本超支。 SPI = EV\u002FPV=4000\u002F4400≈0.9\u003C1，表明进度滞后。 EAC = AC+ETC= AC+（BAC-EV）\u002FCPI=5000+（10000-4000）\u002F0.8=12500元。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]