[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384608,165,1,"单选题","进行项目估算时,需要根据项目的特点等因素,决定采用何种估 算方法。( )方法的准确性会受到所采用估算模型的成熟度和基础 数据可靠性的影响 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专家判断",false,{"key":16,"text":17,"correct":14},"B","类比估算",{"key":19,"text":20,"correct":21},"C","参数估算",true,{"key":23,"text":24,"correct":14},"D","自下而上估算","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]