[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384607,165,1,"单选题","项目的成本估算要经过识别并分析成本的构成科目、估算每一科目的成本大小、分析成本估算结果三个步骤。在第一个步骤中无法形成的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","低成本的替代方案",true,{"key":16,"text":17,"correct":18},"B","会计科目表",false,{"key":20,"text":21,"correct":18},"C","项目资源矩阵",{"key":23,"text":24,"correct":18},"D","项目资源数据表","识别并分析成本的构成科目过程形成项目资源矩阵、会计科目表和与时间相关的项目资源数据表。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]