[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384605,165,1,"单选题","项目经理王某对其负责的系统集成项目进行了成本估算和进度安排，根据团队成员的情况分配了任务，并制定出计划执行预算成本的基准。由于公司高层领导非常重视该项目，特地调配了几名更有经验（薪水更高）的技术骨干参与项目，这种变化对项目绩效造成的最可能影响是 （33） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","正的成本偏差CV，正的进度偏差SV",false,{"key":16,"text":17,"correct":18},"B","负的成本偏差CV，正的进度偏差SV",true,{"key":20,"text":21,"correct":14},"C","正的成本偏差CV，负的进度偏差SV",{"key":23,"text":24,"correct":14},"D","负的成本偏差CV，负的进度偏差SV","技术骨干会产生进度提前的偏差，而付给更高的薪水、出现负的成本偏差。参考答案：（33）B",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]