[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384601,165,1,"单选题","在进行成本估算时，将工作的计划数量与单位数量的历史成本相乘得到估算成本的方法称为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","自下而上估算法",false,{"key":16,"text":17,"correct":14},"B","类比估算法",{"key":19,"text":20,"correct":21},"C","参数估算法",true,{"key":23,"text":24,"correct":14},"D","质量成本估算法","参数估算：是一种运用历史数据和其他变量（如施工中的平方米造价，软件编程中的编码行数，要求的人工小时数，软件项目估算中的功能点方法等）之间的统计关系来计算活动资源成本的估算技术。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]