[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384600":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384600,165,1,"单选题","在某一时刻，项目CPI为1.05，这表示（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目100元的成本创造了105元的价值",true,{"key":16,"text":17,"correct":18},"B","项目100元的成本创造了100元的价值",false,{"key":20,"text":21,"correct":18},"C","项目进度提前了5%",{"key":23,"text":24,"correct":18},"D","项目进度落后了5%","挣值技术。CPI是指成本绩效指数，CPI大于1说明成本节约。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]