[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384595,165,1,"单选题","根据以下布线计划及完成进度表，在2010年6月2日完工后对工程进度和费用进行预测，按此进度，完成尚需估算（ET C）为 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","18 000元",false,{"key":16,"text":17,"correct":18},"B","36 000元",true,{"key":20,"text":21,"correct":14},"C","20 000元",{"key":23,"text":24,"correct":14},"D","54 000元","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]