[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384594,165,1,"单选题","项目经理在制定项目成本预算时采取以下步骤：①估算项目的总成本；②将项目的总成本分解到WBS工作包；③将各个工作包成本再分解到相关活动；④公司对预算草案进行审批围绕该步骤，下列说法中，（）是正确的",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理不应该将各个工作包成本再分解到相关活动",false,{"key":16,"text":17,"correct":14},"B","项目经理采用至上而下分解成本的方法是不对的，应该直接对工作包进行估算",{"key":19,"text":20,"correct":21},"C","该流程中缺乏成本预算支出的时间计划",true,{"key":23,"text":24,"correct":14},"D","预算由项目经理批准即可，不必公司批准","制定项目成本预算所经过的步骤(1)将项目总成本分摊到项目工作分解结构的各个工作包。(2)将各个工作包成本再分配到该工作包所包含的各项活动上。(3)确定各项成本预算支出的时间计划及项目成本预算计划。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]