[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384593,165,1,"单选题","自下而上估算方法是指估算单个工作包或细节详细活动的成本，然后简写详细的成本汇总到更高层级估算的方法，下面关于该方法的描述中（）是错误的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","其精确性取决于估算对象的规模和复杂程度",false,{"key":16,"text":17,"correct":14},"B","便于报告和跟踪",{"key":19,"text":20,"correct":21},"C","适于对项目情况了解较少时采用",true,{"key":23,"text":24,"correct":14},"D","该估算方法的准确性通常高于其他估算方法","本题考查的是自下而上估算方法的基础知识，了解就好。 教程 P284，自下而上估算：包括 ABD，没有 C。如果对项目了解少，则不容易分解，不适合采用此方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]