[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384592":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384592,165,1,"单选题","一般情况下，随着项目的逐渐进展，成本和人员投入水平呈现出①的态势，而项目干系人对于项目最终产品的特征和项目最终费用的影响会②，变更和缺陷修改的费用通常会③。①、②和③分别是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①先增后减，②逐渐减小，③逐渐增加",true,{"key":16,"text":17,"correct":18},"B","①先减后增，②逐渐增加，③逐渐减少",false,{"key":20,"text":21,"correct":18},"C","①先增后减，②逐渐增加，③逐渐增加",{"key":23,"text":24,"correct":18},"D","①先减后增，②逐渐减少，③逐渐减少","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]