[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384591,165,1,"单选题","（）不是系统集成项目的直接成本",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进口设备报关费",false,{"key":16,"text":17,"correct":14},"B","第三方测试费用",{"key":19,"text":20,"correct":14},"C","差旅费",{"key":22,"text":23,"correct":24},"D","员工福利",true,"直接成本：直接可以归属于项目工作的成本为直接成本，属于项目执行过程中直接投入并发生的费用。如项目团队差旅费、工资、项目使用的物料及设备使用费，以及资料费、咨询鉴定费、培训费等。间接成本：来自一般管理费用科目或几个项目共同担负的项目成本所分摊给本项目的费用，就形成了项目的间接成本，如税金、额外福利和保卫费用等。D不属于为完成系统集成项目支付的直接费用，所以不属于直接成本",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]