[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384586,165,1,"单选题","某项目经理已经完成了WBS和每个工作包的成本估算。要根据这些数据编制项目成本估算，该项目经理要()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","使用WBS的最高层次进行类比估算",false,{"key":16,"text":17,"correct":18},"B","计算工作包和风险储备估算的总和",true,{"key":20,"text":21,"correct":14},"C","把工作包估算累计成为项目估算总和",{"key":23,"text":24,"correct":14},"D","获得专家对项目成本总计划意见","除了项目直接成本外，项目估算还需要考虑但容易被忽视的主要因素有以下几种：（1）非直接成本；（2）学习曲线；（3）项目完成的时限（4）质量要求；（5）储备：包括应急储备和管理储备，主要为防范风险所预留的成本。但这部分成本往往被管理层或客户给压缩掉，这是不对的。其作用就像战争中的预备队，是非常重要的。估算必须包括用于风险的储备。这种储备可以是时间或成本的储备。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]