[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384582,165,1,"单选题","项目经理创建了某软件开发项目的WBS工作包，其中一个工作包举例如下：130（注：工作包编号，下同）需求阶段；131需求调研；132需求分析；133需求定义。通过成本估算，131预计花费3万元；132预计花费2万元；133预计花费2.5万元。根据各工作包的成本估算，采用（）方法，能最终形成整个项目的预算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资金限制平衡",false,{"key":16,"text":17,"correct":14},"B","准备金分析",{"key":19,"text":20,"correct":14},"C","成本参数估算",{"key":22,"text":23,"correct":24},"D","成本汇总",true,"成本预算指将单个活动或工作包的估算成本汇总，以确立衡量项目绩效情况的总体成本基准。本题目中创建了WBS工作包，并给出了某工作包的估算结果，得到各工作包估算数据后，需要将这些详细成本汇总到更高层级，以最终形成整个项目的总体预算。故采用的方法为D",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]