[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384574,165,1,"单选题","以下关于项目成本预算的描述，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当项目的具体工作无法确定时，无法进行成本预算",false,{"key":16,"text":17,"correct":14},"B","成本基准计划可以作为度量项目绩效的依据",{"key":19,"text":20,"correct":21},"C","管理储备是为范围和成本的潜在变化而预留的预算，因此需要体现在项目成本基线里",true,{"key":23,"text":24,"correct":14},"D","成本预算过程完成后，可能会引起项目管理计划的更新","管理储备是为范围和成本的潜在变化而预留的预算，它们是“未知的”，项目经理在使用之前必须得到批准。管理储备不是项目成本基线的一部分。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]