[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384573,165,1,"单选题","成本基准是对项目进行成本管控的重要措施，成本基准是指按时间分段的项目（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本估算",false,{"key":16,"text":17,"correct":18},"B","成本预算",true,{"key":20,"text":21,"correct":14},"C","实际成本",{"key":23,"text":24,"correct":14},"D","隐形成本","成本基准是按时间分段的预算，用做度量和监控项目整体成本执行（绩效）的基准。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]