[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384571,165,1,"单选题","公司刚承接了一个系统集成及运行维护的项目，在做集成验收活动的资源估算时，需要综合考虑完成活动的工程师的经验及技能，各种大小或类型的机器，各种测试工具（手工操作或自动化工具），以及所需资源的自制或购买决策等，此种资源估算法为（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自上而下估算",false,{"key":16,"text":17,"correct":18},"B","多方案分析",true,{"key":20,"text":21,"correct":14},"C","专家判断",{"key":23,"text":24,"correct":14},"D","项目管理软件","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]