[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384566,165,1,"单选题","下表是项目甲、乙、丙三个项目的进度数据，则（ ）最有可能在成本的约束内完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目甲",true,{"key":16,"text":17,"correct":18},"B","项目乙",false,{"key":20,"text":21,"correct":18},"C","项目丙",{"key":23,"text":24,"correct":18},"D","项目甲和项目丙","甲CPI=EV\u002FAC=8000\u002F5000>1 乙CPI=EV\u002FAC=5000\u002F8000\u003C1 丙CPI=EV\u002FAC=8000\u002F9000\u003C1 CPI大于1表示资金使用效率高，成本节余，最有可能在成本约束内完成。 计算甲最优。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]