[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384563,165,1,"单选题","下图是某项目成本风险的蒙特卡罗分析图。以下说法中不正确的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","蒙特卡罗分析法也叫随机模拟法",false,{"key":16,"text":17,"correct":14},"B","该图用于风险分析时，可以支持定量分析",{"key":19,"text":20,"correct":21},"C","根据该图，41万元完成的概率是12%，如果要达到75%的概率，需要增加5.根据该图，41万元完成的概率是12%，如果要达到75%的概率，需要增加5.57万元作为应急储备",true,{"key":23,"text":24,"correct":14},"D","该图显示，用45万元的成本也可能完成计划","风险管理、收尾管理、知识产权管理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]